SK hynix orders tools to add 20,000 monthly HBM4 wafers at P&T6
Purchase orders for the converted M8 cleanroom in Cheongju advance high-bandwidth memory packaging capacity for commercial shipments in 2027.
SK hynix began coordinating purchase orders with domestic equipment vendors on Nov. 15, 2026, to equip its Cheongju P&T6 packaging line for sixth-generation high-bandwidth memory production.
The installation will add more than 20,000 wafers per month of HBM4 packaging capacity by filling idle cleanroom areas. That volume represents a crucial interim step for commercial shipments in 2027.
The P&T6 facility occupies a converted fab that previously housed an eight-inch wafer fabrication line known as M8. SK hynix repurposed the site into a dedicated back-end packaging and testing center.
The procurement round builds on initial purchase orders issued in February 2026. SK hynix opened cleanroom facilities at P&T6 in March after converting the former foundry line into packaging halls.
Sixth-generation memory stacks require tighter thermal and physical tolerances than earlier generations. The architecture couples customized logic base dies with memory dies using advanced mass reflow molded underfill — a technique that injects protective epoxy.
SK hynix uses advanced MR-MUF to preserve thermal conductivity across denser memory stacks. The company bypassed hybrid bonding for initial HBM4 production, retaining liquid epoxy encapsulation to protect manufacturing yields.
The latest orders cover die bonding, precision dicing and high-voltage wafer inspection tools. Vendors expect to complete tool delivery and factory setup between the first quarter and the end of June 2027.
Domestic equipment makers are capturing measurable shares of the capital expenditure. UniTest disclosed a 22.38 billion won ($16.3 million) supply contract on July 23 to deliver HBM4 wafer burn-in testers directly to P&T6.
The order represented 20.31% of UniTest's 2025 consolidated revenue of 110.2 billion won ($80.2 million). That agreement followed a separate 29.5 billion won equipment contract signed two months earlier.
UniTest completed qualification testing for its HBM4 wafer burn-in systems during the first quarter of 2026. The vendor produces the test machines domestically without relying on external manufacturing contractors.
Digital Frontier, a 65.18% owned subsidiary of test-equipment maker DI Corp, secured 232.1 billion won ($169 million) in cumulative HBM4 wafer tester orders from SK hynix during 2026.
Its March contract alone was worth 96.25 billion won ($70 million). That single order accounted for roughly 39% of Digital Frontier's 2025 revenue and covered more than 50 wafer test units.
The awards mark a shift away from Japanese supplier Advantest. Advantest historically supplied the vast majority of memory wafer test platforms to South Korean chipmakers before domestic vendors qualified specialized HBM4 tools.
Wafer-level burn-in testing screens dies under extreme temperatures and voltages before slicing. Identifying flawed chips early prevents costly packaging failures across 12-layer and 16-layer memory stacks, the company said.
HBM4 marks the first time memory makers must integrate logic base dies fabricated by external foundries. SK hynix has partnered with Taiwan Semiconductor Manufacturing Co. to manufacture those foundational wafers.
The P&T6 expansion bridges SK hynix's packaging capacity until its larger facility opens. Cheongju already hosts the company's M11, M12, M15 and M15X front-end memory fabrication plants.
SK hynix broke ground on its P&T7 packaging fab in Cheongju on April 22, 2026. The company committed approximately 19 trillion won ($13.8 billion) in total capital expenditures to that greenfield project.
P&T7 will house 150,000 square meters of cleanrooms across several multistory structures. The footprint includes 60,000 square meters for wafer-level packaging and 90,000 square meters for final wafer testing.
The chipmaker's board reapproved 7.09 trillion won ($5.16 billion) of initial spending for P&T7 on July 22. That sum represented 5.88% of the company's total equity at the time.
Management brought forward cleanroom construction schedules at P&T7 to accelerate customer sample qualification. Converting existing space at P&T6 allows SK hynix to meet commercial delivery targets several quarters earlier.
AI accelerator designer Nvidia remains the primary destination for SK hynix's advanced memory output. Nvidia adjusted bandwidth targets for its upcoming Vera Rubin architecture, simplifying high-volume assembly for memory suppliers.
SK hynix stated during its third-quarter earnings briefing that high-bandwidth memory capacity was effectively committed through 2029. Long-term supply agreements have insulated capital spending decisions from spot memory market fluctuations.
The company has not published regulatory filings detailing aggregate tool procurement values for P&T6. SK hynix has also withheld official delivery milestones for the remaining cleanroom space inside the converted building.
Equipment vendors must finalize factory acceptance tests before tool delivery begins in January 2027. SK hynix plans to install initial testing lines at P&T7 in October 2027.
Trial packaging runs on the newly equipped P&T6 lines will begin before commercial wafer deliveries ramp in the second half of 2027.
Impact map
How this development propagates across the region and out to global buyers.
| Event | Korea | China | Japan | Global impact |
|---|---|---|---|---|
| HBM4 packaging tool orders | SK hynix secures 20,000 monthly wafer run rate while UniTest books 20.3% of annual sales | CXMT remains two generations behind on HBM packaging yields | Advantest loses wafer test exclusivity at SK hynix to Korean suppliers | Nvidia secures qualified 2027 HBM4 packaging supply for Vera Rubin architecture |
In this story
Related briefings
- SK hynix delays HBM4 equipment procurement into early 2027 Also on UniTest, SK hynix, Order Book
- SK hynix Convenes Japan Chip Suppliers on Next HBM Roadmap Also on Advantest, SK hynix
- Samsung begins building $4.5B Onyang advanced packaging fab Also on Nvidia, SK hynix, Order Book
- South Korea reviews 260,000 Nvidia GPU deliveries after CEO exit Also on Nvidia, SK hynix, Order Book
Sources
Primary documents
Reporting
Confidence: high — how we grade this
The documents behind this briefing are linked above. East Asia Brief produces its English text with AI assistance under human editorial review, and does not translate or republish other outlets' articles. See our methodology and AI policy. Spotted an error? Tell us.