# Westinghouse qualifies new nuclear suppliers amid forging crunch

*Purchase orders for BWXT Canada to fabricate steam generator parts underline shortages of ultra-heavy forging presses for 14 AP1000 projects.*

**Published:** November 25, 2026  
**By:** So-yeon Jung  
**Section:** Energy & Critical Minerals — South Korea  
**Format:** Why It Matters  
**Confidence:** high  
**Source:** https://eastasiabrief.com/energy-minerals/westinghouse-qualifies-new-nuclear-suppliers-amid-forging-crunch-1755  
**Publisher:** East Asia Brief (https://eastasiabrief.com/)

---

## What to know

- Westinghouse qualified BWXT on Nov. 24 as US nuclear developers face forging bottlenecks
- Doosan Enerbility operates a 17,000-ton press and supplied four of six operating AP1000s
- SMR commercial deployment targets early 2030s while MOTIE launches US export support in 2027

![Westinghouse qualifies new nuclear suppliers amid forging crunch](https://eastasiabrief.com/media/2026-11-25-64751e1384d5.webp)

Westinghouse Electric Company issued qualification purchase orders Nov. 24 to expand its North American reactor supply chain, underscoring component manufacturing bottlenecks facing planned nuclear expansions across the United States.

The agreement qualifies BWXT Canada to fabricate demonstration pieces for steam generators and reactor internals across facilities in Ontario and Pennsylvania, according to company notices.

Westinghouse currently supports 14 AP1000 reactors under construction globally alongside six operating units, but Western developers face severe shortages of the ultra-heavy forging presses needed to produce primary reactor pressure vessels.

Surging electricity consumption from artificial intelligence data centers has accelerated US utility interest in nuclear capacity, yet the domestic industrial base has not forged a commercial nuclear vessel in decades.

A single 1,100-megawatt reactor requires thousands of tons of high-integrity forged steel capable of withstanding intense neutron radiation and operating pressures exceeding 150 atmospheres for 60 to 80 years.

Industry filings indicate that procuring large-diameter forgings remains the primary critical-path risk for American nuclear projects, with global lead times for forged reactor heads currently exceeding 48 months.

South Korea's Doosan Enerbility operates a 17,000-ton forging press at its Changwon complex, the largest four-pillar hydraulic press currently active in the commercial nuclear power industry.

The 17,000-ton press in Changwon operates alongside a 13,000-ton press, allowing workers to process steel ingots weighing more than 500 tons into seamless cylindrical vessel rings.

The Changwon facility uses ring-forged shells and closed-die heads to eliminate longitudinal welds, cutting factory assembly schedules and reducing subsequent in-service ultrasonic inspection requirements for plant operators.

Doosan Enerbility has manufactured and shipped 34 reactor vessels and 124 steam generators worldwide, maintaining the heavy fabrication workforce that North American and European heavy engineering firms largely dismantled.

The South Korean manufacturer previously supplied critical reactor pressure vessels and steam generator channel heads for four of the six operational AP1000 units globally, including Georgia Power's Vogtle Units 3 and 4.

BWX Technologies operates 19 manufacturing facilities globally and employs 11,000 people, but its qualification contracts with Westinghouse cover only initial demonstration pieces, the companies said.

Steam generators — massive heat exchangers that transfer thermal energy from primary reactor coolant to secondary turbine loops — require specialized alloy tubing and forged tube sheets weighing up to 130 tons each.

Doosan Enerbility signed a contract in July to supply eight ultra-large steam generator forgings through 2029 for two CAP1400 units in China, illustrating steady factory utilization that keeps fabrication lines warm.

Modular construction techniques require fabricators to assemble pre-engineered structural blocks offsite, moving work from complex field construction sites into controlled factory environments to prevent multi-year schedule slippage.

South Korea's Ministry of Trade, Industry and Energy discussed an intergovernmental nuclear framework at an industry conference in late October, projecting the construction of up to eight large-scale reactors on US soil.

Under discussions surrounding that bilateral framework, South Korean equipment manufacturers and construction engineering contractors would supply core components, positioning domestic heavy industry to capture billions of dollars in nuclear hardware orders.

The ministry plans to roll out specialized export support initiatives in 2027 to assist domestic component vendors with US regulatory codes and supplier qualification audits.

The procurement crunch extends directly to small modular reactors, where developers are competing for identical heavy forging capacity and certified nuclear manufacturing slots.

Doosan Enerbility executed a procurement contract Nov. 4 with Swedish tube maker Alleima to produce helical steam generator coils for X-energy's 320-megawatt Xe-100 high-temperature gas-cooled reactor project in Texas.

Doosan Enerbility also holds capacity reservation agreements covering 16 reactor vessel sets for X-energy, locking in Changwon fabrication capacity ahead of scheduled commercial deployment in the early 2030s.

For Western project sponsors, securing Korean heavy forging slots shortens long-lead component delivery windows from roughly seven years down to four years, according to nuclear procurement filings.

The South Korean government and domestic industry groups have not published an official filing or primary notice confirming a formal modular manufacturing alliance on Nov. 24, leaving corporate equity splits and commercial delivery commitments unverified.

Westinghouse and BWXT Canada are scheduled to review demonstration component fabrication milestones through 2027 before determining commercial procurement volumes for future AP1000 builds.

## Impact map

| Event | Korea | China | Japan | Global impact |
| --- | --- | --- | --- | --- |
| US nuclear component bottleneck | Doosan Enerbility leverages 17,000-ton press to secure reactor vessel orders | Domestic yards build CAP1400 units, relying partly on imported forgings | Japan Steel Works maintains heavy forging capacity but faces full order books | Nuclear capital costs hinge on 48-month lead times for primary island forgings |

## In this story

- **Companies:** Doosan Enerbility, Westinghouse Electric Company, BWX Technologies
- **Tickers:** 034020.KS, BWXT
- **Exposed:** X-energy, Alleima
- **Policy:** Procurement Rules, Subsidies
- **Impact:** Supply Chain, Order Book, Capex

## Primary sources

1. gen.or.kr <http://www.gen.or.kr/news/index.php?page=3&page=11>
2. snu.ac.kr <https://atomic.snu.ac.kr/%EA%B5%AD%EC%A0%9C_%EC%9B%90%EC%9E%90%EB%A0%A5_%EB%8F%99%ED%96%A5_%EC%9D%BC%EC%9D%BC_%EB%B8%8C%EB%A6%AC%ED%95%91_2026-11-24>
3. bwxt.com <https://www.bwxt.com/westinghouse-canada-awards-bwxt-ap1000-manufacturing-qualification-contracts/>
4. westinghousenuclear.com <https://info.westinghousenuclear.com/en-ca/news-insights/westinghouse-canada-awards-bwxt-ap1000-manufacturing-qualification-contracts>

---

Cite as: East Asia Brief, "Westinghouse qualifies new nuclear suppliers amid forging crunch," November 25, 2026. https://eastasiabrief.com/energy-minerals/westinghouse-qualifies-new-nuclear-suppliers-amid-forging-crunch-1755